DMC Pediatric Specialty Center

Detroit, MI – 612 Tons

This 83,500 sq.ft. new construction project involved an extremely tight site and a firm budget. Douglas Steel Fabricating Corporation provided fabrication and erection for Brinker LLC, navigating an urban area around existing hospital structures.  Douglas coordinated just-in-time delivery of steel for the day of erection, which enabled the construction team to minimize site storage requirements without delaying progress.  Timing was also a critical element when setting the basement columns; each time it rained, the site basin filled with water, hindering work.  Douglas worked side-by-side with the EOR to address these challenges and identify solutions to keep the project moving.